Who
NOSi / CME
What
Mechanical EPC Services
When
Operational Since 2018
Where
Santiago Island, Cabo Verde
Systems
1x 1600 kVA Perkins Engine + 1x 1100 kVA Perkins Engine
Type
Data Centre Emergency Backup
Telefone: +351 987 654 321
Email: teste@winpower.com
Cabo Verde
As part of the construction of the Technology Park Cabo Verde – NOSi Data Centre, the emergency backup power station is considered a critical component of all infrastructure. It guarantees its non-stop operation profile, crucial in Data Centre facilities.
NOSi is a public business entity (EPE), and the implementation of this project aims to promote innovation and e-governance, support public policies in the field of information and communication technologies and e-governance, and guarantee security and data protection of the State, among others.
WinPower designed, supplied, installed, and commissioned an emergency power station with two containerized diesel gensets PRP mode, equipped with all the related auxiliary systems and a local HHI interface system.
The control system was prepared for load demand / baseload and load sharing able to start in case of an energy supply fault with a communication interface with the Data Center SCADA system.
Who
NOSi / CME
What
Mechanical EPC Services
When
Operational Since 2018
Where
Santiago Island, Cabo Verde
Systems
1x 1600 kVA Perkins Engine + 1x 1100 kVA Perkins Engine
Type
Data Centre Emergency Backup
WinPower delivered a turnkey solution for the mechanical and electrical equipment of the Emergency Power Station. We ensured the continued operation of the installation without interruptions and delivered a reliable, robust, and state-of-the-art solution, from design to engineering and construction.
Energy solutions designed and engineered by a team of experienced experts in the field.
Fogo Island
Cabo Verde
Part of Cabo Verde’s ongoing investment plans to enhance energy [...]
Boavista
Cabo Verde
Green, reliable, and affordable energy is one of the sustainable drivers solving [...]
Santarém
Portugal
The project was the result of the Portuguese ongoing investment plans [...]