Santiago Island

Cabo Verde

NOSi – Design Technology Park
Cabo Verde Emergency Power Plant

As part of the construction of the Technology Park Cabo Verde – NOSi Data Centre, the emergency backup power station is considered a critical component of all infrastructure. It guarantees its non-stop operation profile, crucial in Data Centre facilities.

NOSi is a public business entity (EPE), and the implementation of this project aims to promote innovation and e-governance, support public policies in the field of information and communication technologies and e-governance, and guarantee security and data protection of the State, among others.

santiago island

Our Solution

WinPower designed, supplied, installed, and commissioned an emergency power station with two containerized diesel gensets PRP mode, equipped with all the related auxiliary systems and a local HHI interface system.

The control system was prepared for load demand / baseload and load sharing able to start in case of an energy supply fault with a communication interface with the Data Center SCADA system.

cliente preview rev 1

Who

NOSi / CME

servicos preview rev 1

What

Mechanical EPC Services

operational since preview rev 1

When

Operational Since 2018

localizacao preview rev 1

Where 

Santiago Island, Cabo Verde

systems preview rev 1

Systems

1x 1600 kVA Perkins Engine + 1x 1100 kVA Perkins Engine

type preview rev 1

Type

Data Centre Emergency Backup

The Results

WinPower delivered a turnkey solution for the mechanical and electrical equipment of the Emergency Power Station. We ensured the continued operation of the installation without interruptions and delivered a reliable, robust, and state-of-the-art solution, from design to engineering and construction.

Other Engineering Projects

Energy solutions designed and engineered by a team of experienced experts in the field.

EPC CONTRACT THERMAL POWER PLANT

Fogo Island

Cabo Verde

EPC CONTRACT THERMAL POWER PLANT

Part of Cabo Verde’s ongoing investment plans to enhance energy  [...]

Read More

FEASIBILITY STUDIES HYBRID GENERATION

Boavista


Cabo Verde

FEASIBILITY STUDIES HYBRID GENERATION

Green, reliable, and affordable energy is one of the sustainable drivers solving  [...]

Read More

BIOMASS POWER PLANT

Santarém

Portugal

BIOMASS POWER PLANT

The project was the result of the Portuguese ongoing investment plans [...]

Read More